7820 N SHIRLEY AVE 91335

Certificate Information: 7820 N SHIRLEY AVE 91335

Application / Permit
21016-20000-11337
Plan Check / Job No.
B21VN05408
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-10" X 26'-0" DETACAHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 RAPHAEL ROSAS
Corrections Issued 5/14/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/7/2021 RAPHAEL ROSAS
Issued 1/19/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
CofO in Progress 7/29/2022 JEFFREY BULL
CofO Issued 4/20/2023 MICHAEL SMITH
Permit Finaled 4/20/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/24/2021 GABRIEL ROBLES
Sewer availability Cleared 5/24/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/17/2021 GABRIEL ROBLES
Construction near power lines Cleared 11/19/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/17/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/17/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/17/2022 Approved VINCENT HANLEY
Sewer 2/17/2022 Approved VINCENT HANLEY
Underground Mechanical 2/17/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/7/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 3/7/2022 Approved VINCENT HANLEY
Green Building Rough 3/7/2022 Corrections Issued VINCENT HANLEY
HVAC-Rough 3/7/2022 Approved VINCENT HANLEY
PLUMBING-Rough 3/7/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/11/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Approved VINCENT HANLEY
Green Building Rough 3/11/2022 Approved VINCENT HANLEY
Insulation 3/11/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/11/2022 Approved VINCENT HANLEY
Drywall Nailing 3/15/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Final 4/21/2022 Corrections Issued VINCENT HANLEY
Final 4/21/2022 Corrections Issued VINCENT HANLEY
Green Building Final 4/21/2022 Approved VINCENT HANLEY
HVAC-Final 4/21/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/21/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 5/2/2022 Approved VINCENT HANLEY
Final 5/2/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 5/2/2022 Approved VINCENT HANLEY
PLUMBING-Final 5/2/2022 Approved VINCENT HANLEY
Final 7/29/2022 OK to Issue CofO JEFFREY BULL