21520 W VELICATA ST 91364

Certificate Information: 21520 W VELICATA ST 91364

Application / Permit
21016-20000-11169
Plan Check / Job No.
B21VN05302
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) SFD TO REMOVE LOAD-BEARING WALLS IN DINING ROOM TO CREATE AN OPEN FLOOR PLAN LAYOUT AND REMOVE & REPLACE EXTERIOR DOORS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 6/11/2021
Issuing Office
Current Status
Permit Finaled on 6/28/2022

Permit Application Status History

Submitted 4/30/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 GURUNATH NESARAJAH
Corrections Issued 5/9/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 5/29/2021 GURUNATH NESARAJAH
Plan Check Approved 6/11/2021 GURUNATH NESARAJAH
Issued 6/11/2021 APPLICANT
Building Plans Picked Up 6/14/2021 APPLICANT
Permit Finaled 6/27/2022 PETER FOLLING

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/11/2021 GURUNATH NESARAJAH

Contact Information

Contractor Dileone Construction; Lic. No.: 1061219-B 4675 GALENDO STREET      WOODLAND HILLS, CA 91364
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2021 Approved HENRY KIM
PLUMBING-Rough 6/18/2021 Not Ready for Inspection HENRY KIM
Deputy Drilled-In Anchors 8/13/2021 No Access for Inspection PETER FOLLING
ELECTRICAL-Rough 8/16/2021 Approved PETER FOLLING
HVAC-Rough 8/16/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 8/16/2021 Approved PETER FOLLING
Sewer 8/16/2021 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 8/18/2021 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Approved PETER FOLLING
HVAC-Rough 8/18/2021 Approved PETER FOLLING
Sewer 8/18/2021 Approved PETER FOLLING
Insulation 8/27/2021 Approved PETER FOLLING
Deputy Drilled-In Anchors 9/17/2021 No Access for Inspection PETER FOLLING
ELECTRICAL-Final 6/3/2022 Not Ready for Inspection PETER FOLLING
Final 6/3/2022 Corrections Issued PETER FOLLING
HVAC-Final 6/3/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Final 6/3/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Approved PETER FOLLING
Smoke Detectors 6/3/2022 Approved PETER FOLLING
Final 6/27/2022 Permit Finaled PETER FOLLING
HVAC-Final 6/27/2022 Approved PETER FOLLING
PLUMBING-Final 6/27/2022 Approved PETER FOLLING