10465-10467 N ETON AVE 91311

Certificate Information: 10465-10467 N ETON AVE 91311

Application / Permit
21016-20000-11111
Plan Check / Job No.
B21VN05284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (420 SQ FT) PER LAMC 12.22 A.33(c) and (e). ALL WORK PER WFPP.
Permit Issued
Issued on 6/25/2021
Issuing Office
Current Status
CofO Issued on 9/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 JEROME MAGAT PALMA
Corrections Issued 4/30/2021 JEROME MAGAT PALMA
Plan Check Approved 6/3/2021 SARKIS HARABEDIAN
Building Plans Picked Up 6/7/2021 APPLICANT
Issued 6/25/2021 APPLICANT
CofO in Progress 4/22/2022 TROY SANDERS
CofO Issued 9/12/2022 DANIEL ORRANTE
Permit Finaled 9/12/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/3/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/3/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/3/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 11/5/2021 Approved JEFFREY PARD
Underground Mechanical 11/5/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/28/2021 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 12/28/2021 Approved JEFFREY PARD
Green Building Rough 12/28/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 2/1/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Approved JEFFREY PARD
HVAC-Rough 2/1/2022 Approved JEFFREY PARD
PLUMBING-Rough 2/1/2022 Approved JEFFREY PARD
Drywall Nailing 2/16/2022 Approved JUSTIN HAWLEY
Insulation 2/16/2022 Approved JUSTIN HAWLEY
Special/Order Compliance 3/2/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/24/2022 Approved TROY SANDERS
Final 3/24/2022 Corrections Issued TROY SANDERS
Green Building Final 3/24/2022 Approved TROY SANDERS
Green Building Rough 3/24/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 3/24/2022 Approved TROY SANDERS
Final 4/22/2022 OK to Issue CofO TROY SANDERS