16625 W CHATSWORTH ST 91344

Certificate Information: 16625 W CHATSWORTH ST 91344

Application / Permit
21016-20000-11108
Plan Check / Job No.
B21VN05283
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E)18' x 20' DET. GRARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
Permit Issued
Issued on 6/10/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 JEFFREY TANGONAN
Corrections Issued 5/1/2021 JEFFREY TANGONAN
Building Plans Picked Up 5/4/2021 APPLICANT
Plan Check Approved 5/21/2021 JEFFREY TANGONAN
Issued 6/10/2021 APPLICANT
CofO in Progress 2/1/2023 JAVIER RAMOS JR
Permit Finaled 2/8/2023 MICHAEL SMITH
CofO Issued 2/8/2023 MICHAEL SMITH
Permit Finaled 2/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/5/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/5/2021 GUILLERMO PETRA
Sewer availability Cleared 5/5/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/26/2022 Approved JAVIER RAMOS JR
Sewer 7/26/2022 Approved JAVIER RAMOS JR
Underground Mechanical 7/26/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/10/2022 Approved JAVIER RAMOS JR
HVAC-Rough 8/10/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 8/10/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/26/2022 Approved DEANDRE HOFFMAN
Green Building Rough 8/26/2022 Approved DEANDRE HOFFMAN
HVAC-Rough 8/26/2022 Approved DEANDRE HOFFMAN
Insulation 8/26/2022 Approved DEANDRE HOFFMAN
Shower Pan 8/26/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 9/2/2022 Approved JAVIER RAMOS JR
Final 10/31/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/31/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 10/31/2022 Approved JAVIER RAMOS JR
Final 11/10/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 11/10/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved JAVIER RAMOS JR
Pre-Inspection 1/6/2023 Approved JAVIER RAMOS JR