2835 W ANGUS ST 90039

Certificate Information: 2835 W ANGUS ST 90039

Application / Permit
21016-20000-10819
Plan Check / Job No.
B21VN05117
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/9/2021
Issuing Office
Valley
Current Status
CofO Issued on 7/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 5/4/2021 JEROME MAGAT PALMA
Corrections Issued 5/4/2021 JEROME MAGAT PALMA
Plan Check Approved 8/22/2021 JEROME MAGAT PALMA
Building Plans Picked Up 8/25/2021 APPLICANT
Issued 9/9/2021 APPLICANT
CofO in Progress 7/12/2022 JOSEPH MCGARRY
Permit Finaled 7/13/2022 DEROLD HAUFF
CofO Issued 7/13/2022 DEROLD HAUFF
Permit Finaled 7/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/30/2021 CECILIO NAVARRO
Sewer availability Cleared 7/30/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/3/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/14/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/17/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 9/17/2021 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 10/6/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/6/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 10/6/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/13/2021 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 10/13/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/13/2021 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/8/2022 Approved JOSEPH MCGARRY
Final 7/8/2022 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 7/8/2022 Approved JOSEPH MCGARRY
Green Building Rough 7/8/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/8/2022 Approved JOSEPH MCGARRY