5754 N VANTAGE AVE 91607
Certificate Information: 5754 N VANTAGE AVE 91607
- Application / Permit
- 21016-20000-10811
- Plan Check / Job No.
- B21VN05110
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION TO (E) SFD TO REMOVE (E) 10' X 18'5" BREEZWAY BETWEEN SFD AND GARAGE AND ADD NEW 18'5" X 14'3" FOR NEW BEDROOM AND BATHROOM , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2021 | RARES BODEA |
| Corrections Issued | 4/28/2021 | RARES BODEA |
| Plan Check Approved | 6/8/2021 | RARES BODEA |
| Issued | 6/8/2021 | APPLICANT |
| Building Plans Picked Up | 6/10/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
| CofO Issued | 2/17/2022 | MICHAEL SMITH |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Supreme Remodeling Inc; Lic. No.: 939981-B | 14545 VICTORY BLVD UNIT 401 VAN NUYS, CA 91411 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/9/2021 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 7/16/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 7/21/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/21/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/12/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/12/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/12/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/12/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 8/16/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/18/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 8/18/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/26/2021 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/30/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/30/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/5/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 10/19/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/8/2021 | Approved | JACK KARGODORIAN |
| Final | 11/8/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/8/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 11/8/2021 | Approved | JACK KARGODORIAN |
| Final | 11/18/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Final | 11/30/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |