1955 S BUCKINGHAM ROAD 90016
Certificate Information: 1955 S BUCKINGHAM ROAD 90016
- Application / Permit
- 21016-20000-10808
- Plan Check / Job No.
- B21VN05108
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 11/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/6/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/15/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/19/2021 | APPLICANT |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 10/31/2022 | STUART CHAPMAN |
| No Progress | 10/31/2022 | STUART CHAPMAN |
| CofO in Progress | 10/31/2022 | STUART CHAPMAN |
| CofO in Progress | 11/18/2022 | STUART CHAPMAN |
| CofO Issued | 11/30/2022 | DEROLD HAUFF |
| Permit Finaled | 11/30/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2021 | ROSA SILVA |
| Sewer availability | Cleared | 5/14/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | ROSA SILVA |
| Construction near power lines | Cleared | 7/16/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Level Frame Construction Inc; Lic. No.: 1078493-B | 1834 W 84TH PL LOS ANGELES, CA 90047 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 4/28/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 4/28/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/11/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 5/11/2022 | Approved | STUART CHAPMAN |
| Insulation | 5/11/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/11/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/20/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 6/27/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/25/2022 | Approved | STUART CHAPMAN |
| Final | 8/25/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/25/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/25/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 8/25/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 10/5/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 10/5/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/28/2022 | Approved | STUART CHAPMAN |
| Final | 10/28/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 10/28/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 10/28/2022 | Approved | STUART CHAPMAN |
| Final | 11/18/2022 | OK to Issue CofO | STUART CHAPMAN |