943 W KENSINGTON ROAD 90026
Certificate Information: 943 W KENSINGTON ROAD 90026
- Application / Permit
- 21016-20000-10767
- Plan Check / Job No.
- B21VN05090
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE/STORAGE/REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d) AND (N) STORAGE AND PANTRY. "COMPLY WITH DEPARTMENT ORDER effective date 03/16/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 5/1/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/16/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/6/2021 | SERGIO MUNIZ |
| Issued | 7/6/2021 | APPLICANT |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| CofO in Progress | 7/14/2022 | PATRICK LIEBREGT |
| Permit Finaled | 8/1/2022 | DANIEL SANCHEZ |
| CofO Issued | 8/1/2022 | DANIEL SANCHEZ |
| Permit Finaled | 8/1/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/17/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | CELINA MORENO |
| HPOZ | Cleared | 6/13/2021 | CHRISTINA PARK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jung,, Jiwon; Lic. No.: C89281 | 3466 BONITA AVE SANTA CLARA, CA 95051 |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2021 | Corrections Issued | PATRICK LIEBREGT |
| Pre-Inspection | 10/13/2021 | Partial Inspection | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 4/11/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Partial Approval | PATRICK LIEBREGT |
| Footing/Foundation/Slab | 4/11/2022 | Partial Approval | PATRICK LIEBREGT |
| Green Building Rough | 4/11/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Pre-Inspection | 4/11/2022 | Approved | PATRICK LIEBREGT |
| Wood Frame | 4/11/2022 | Corrections Issued | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | PATRICK LIEBREGT |
| Final | 6/7/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Green Building Final | 6/7/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Green Building Rough | 6/7/2022 | Approved | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Not Ready | PATRICK LIEBREGT |
| Smoke Detectors | 6/7/2022 | Partial Inspection | PATRICK LIEBREGT |
| Final | 6/10/2022 | Corrections Issued | PATRICK LIEBREGT |
| Green Building Final | 6/10/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | PATRICK LIEBREGT |
| Smoke Detectors | 6/10/2022 | Approved | PATRICK LIEBREGT |
| Final | 7/7/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Green Building Final | 7/7/2022 | Not Ready for Inspection | PATRICK LIEBREGT |
| Service/Power Release | 7/7/2022 | Approved | PATRICK LIEBREGT |
| Final | 7/14/2022 | OK to Issue CofO | PATRICK LIEBREGT |
| Green Building Final | 7/14/2022 | Approved | PATRICK LIEBREGT |