8603 N DARBY AVE 91325
Certificate Information: 8603 N DARBY AVE 91325
- Application / Permit
- 21016-20000-10722
- Plan Check / Job No.
- B21VN05019
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- REMODEL NEW FRONT FACADE
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 3/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | ALYSSA N NARCISO |
| Corrections Issued | 6/9/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 6/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| Applicant returned to address corrections | 7/7/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 7/14/2021 | ALYSSA N NARCISO |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | DEANDRE HOFFMAN |
| Permit Finaled | 3/29/2023 | DEANDRE HOFFMAN |
| CofO Issued | 3/31/2023 | JEFFREY DURAN |
| Permit Finaled | 3/31/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/24/2021 | MIGUEL GAMBOA |
| Encroachment in public way | Cleared | 6/29/2021 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 7/1/2021 | ALYSSA N NARCISO |
Contact Information
| Architect | 3786, La Crescenta Ave; Lic. No.: C34021 | 201 LOS ANGELES COUNTY, AS 91208 |
| Contractor | K & J General Construction; Lic. No.: 1063795-B | 539 S ARIZONA AVENUE LOS ANGELES, CA 90022 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wall Anchors | 12/9/2021 | Corrections Issued | JEFFREY FULTON |
| Wall Anchors | 12/10/2021 | Corrections Issued | JEFFREY FULTON |
| Light Gage Steel Frame | 1/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 1/20/2022 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 2/8/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 1/24/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 1/24/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 1/24/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Not Required | DEANDRE HOFFMAN |
| Smoke Detectors | 1/24/2023 | Approved | DEANDRE HOFFMAN |
| Wall Anchors | 1/24/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 3/20/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Reinforced Masonry Frame | 3/20/2023 | Approved | DEANDRE HOFFMAN |