4216 W 58TH PL 90043

Certificate Information: 4216 W 58TH PL 90043

Application / Permit
21016-20000-10660
Plan Check / Job No.
B21VN05008
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' x 18' GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofO Issued on 2/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 JEFFREY TANGONAN
Corrections Issued 5/1/2021 JEFFREY TANGONAN
Issued 6/10/2021 APPLICANT
Building Plans Picked Up 6/11/2021 APPLICANT
CofO in Progress 11/28/2022 ENRIQUE MIRELES
Permit Finaled 2/21/2023 DEROLD HAUFF
CofO Issued 2/21/2023 DEROLD HAUFF
Permit Finaled 2/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2021 CECILIO NAVARRO
Sewer availability Cleared 5/17/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/25/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 6/1/2021 PATRICK MISCHLICH

Contact Information

Contractor Best Solar Power Inc; Lic. No.: 988425-B 17609 VENTURA BLVD #LL08      ENCINO, CA 91316

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2021 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/15/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/18/2021 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/23/2021 Corrections Issued ADAM ESCOTO
Underground Mechanical 11/23/2021 Corrections Issued ADAM ESCOTO
Footing/Foundation/Slab 11/30/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 11/30/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 1/21/2022 Approved LILIANA PORTILLO
HVAC-Rough 1/21/2022 Approved LILIANA PORTILLO
Insulation 1/21/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 1/21/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/28/2022 Approved FREDDIE RIVERA
Pre-Inspection 1/28/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 2/2/2022 Approved FREDDIE RIVERA
Wood Frame 2/2/2022 Approved FREDDIE RIVERA
Insulation 2/15/2022 Corrections Issued FREDDIE RIVERA
Wood Frame 2/15/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Inspection FREDDIE RIVERA
Insulation 3/1/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 3/1/2022 Approved FREDDIE RIVERA
Sewer 3/1/2022 Approved FREDDIE RIVERA
Wood Frame 3/1/2022 Approved FREDDIE RIVERA
Insulation 4/7/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/7/2022 Approved ENRIQUE MIRELES
Drywall Nailing 4/19/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/19/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 5/23/2022 Approved ANTHONY EGSON
Final 6/2/2022 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 6/2/2022 Approved ENRIQUE MIRELES
METHANE-Final 6/2/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 6/2/2022 Approved ENRIQUE MIRELES
Special/Order Compliance 1/5/2023 Corrections Issued ENRIQUE MIRELES