626 1/2 W 117TH ST 90044

Certificate Information: 626 1/2 W 117TH ST 90044

Application / Permit
21016-20000-10658
Plan Check / Job No.
B21VN05007
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481. ALL WORK PER WFPP.
Permit Issued
Issued on 8/27/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 HAYATO TSUCHIYA
Application Withdrawn-Void 5/27/2021 ALDO UBAU
Re-Activate Application 5/27/2021 ALDO UBAU
Corrections Issued 7/2/2021 HAYATO TSUCHIYA
Plan Check Approved 8/20/2021 HAYATO TSUCHIYA
Issued 8/27/2021 APPLICANT
Building Plans Picked Up 8/31/2021 APPLICANT
CofO in Progress 9/29/2022 ALIZAH MAYAGOITIA
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/25/2021 CECILIO NAVARRO
Sewer availability Cleared 5/25/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/10/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/15/2021 Conditional Approval ANSON MAGLASANG
Green Building Rough 11/15/2021 Not Ready for Inspection ANSON MAGLASANG
MERV13>=Rough 11/15/2021 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 11/15/2021 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 12/29/2021 Conditional Approval EUGENE CASSIDY
ELECTRICAL-Rough 12/29/2021 Approved EUGENE CASSIDY
Green Building Rough 12/29/2021 Approved EUGENE CASSIDY
Insulation 12/29/2021 Corrections Issued EUGENE CASSIDY
Shower Pan 12/29/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/8/2022 Approved JOHN KLARIN
Insulation 2/8/2022 Approved JOHN KLARIN
Drywall Nailing 2/28/2022 Approved JOHN KLARIN
Service/Power Release 2/28/2022 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 3/10/2022 Approved JOHN KLARIN
Service/Power Release 3/21/2022 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 8/30/2022 Not Ready for Inspection ANSON MAGLASANG
Final 8/30/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 8/30/2022 Approved ANSON MAGLASANG
MERV13>=Final 8/30/2022 Approved ANSON MAGLASANG
MERV13>=Rough 8/30/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 8/30/2022 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 9/22/2022 Approved ALIZAH MAYAGOITIA
Final 9/22/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 9/22/2022 Approved ALIZAH MAYAGOITIA
Final 9/29/2022 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 9/29/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/29/2022 Approved ALIZAH MAYAGOITIA
Verify Rec and Parks Fee Memo 9/29/2022 Approved ALIZAH MAYAGOITIA