923 S THAYER AVE 90024

Certificate Information: 923 S THAYER AVE 90024

Application / Permit
21016-20000-10467
Plan Check / Job No.
B21VN04914
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED REC ROOM TO ACCESSORY DWELLING UNIT (256 SQ FT) PER LAMC 12.22 A.33(c) and (d). RELOCATE TOILET. CHANGE OUT DOORS AND WINDOWS. REMOVE AND REPLACE DRY ROT DAMAGED PORTIONS OF BUILDING. ALL WORK PER ENGINEER.
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 6/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 JEROME MAGAT PALMA
Corrections Issued 5/1/2021 JEROME MAGAT PALMA
Plan Check Approved 6/21/2021 JEROME MAGAT PALMA
Issued 10/26/2021 APPLICANT
Building Plans Picked Up 10/28/2021 APPLICANT
CofO in Progress 6/13/2023 MICHAEL PELHAM
Permit Finaled 6/13/2023 DANIEL ORRANTE
CofO Issued 6/13/2023 DANIEL ORRANTE
Permit Finaled 6/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 9/28/2021 ROBERT SANCHEZ
Address approval Cleared 10/14/2021 DINAH GARIN
Sewer availability Cleared 10/14/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/18/2021 DINAH GARIN

Contact Information

Contractor Struct 1 Builders Inc; Lic. No.: 792134-B 16217 KITTRIDGE ST      VAN NUYS, CA 91406
Engineer Ng,, Edward T W; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/29/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 11/1/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 11/1/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 11/1/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 11/10/2021 No Access for Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 1/20/2022 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 2/9/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 2/9/2022 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 2/9/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 2/22/2022 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 2/22/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 3/31/2022 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 3/31/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 3/31/2022 Approved BRENDAN LOONEY
Insulation 4/7/2022 Approved BRENDAN LOONEY
Wood Frame 4/7/2022 Approved BRENDAN LOONEY
Drywall Nailing 4/19/2022 Approved BRENDAN LOONEY
Shower Pan 4/28/2022 Corrections Issued CLAYTON GRAHAM
Shower Pan 5/2/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/10/2022 Approved BRENDAN LOONEY
Shower Pan 5/10/2022 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 9/22/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 9/22/2022 Corrections Issued STEPHANIE SWANSON
Final 9/22/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Final 9/22/2022 Approved STEPHANIE SWANSON
METHANE-Final 9/22/2022 Approved STEPHANIE SWANSON
METHANE-Rough 9/22/2022 Approved STEPHANIE SWANSON
PLUMBING-Final 9/22/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 9/22/2022 Approved STEPHANIE SWANSON
Final 11/9/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved STEPHANIE SWANSON
Final 5/25/2023 Conditional Approval BRENDAN LOONEY