15906-15908 W GRESHAM ST 91343
Certificate Information: 15906-15908 W GRESHAM ST 91343
- Application / Permit
- 21016-20000-10454
- Plan Check / Job No.
- B21VN04902
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 14'-6" X 13'-8" PORTION OF THE (E) SFD, AND THE (E) 22'-6" X 21' ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP. SEE COMMENT.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2021 | PARISA ZAHABI |
| Corrections Issued | 4/28/2021 | PARISA ZAHABI |
| Plan Check Approved | 7/14/2021 | PARISA ZAHABI |
| Issued | 7/14/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 1/24/2023 | RAUL OLAGI |
| CofO Issued | 2/6/2023 | MICHAEL SMITH |
| Permit Finaled | 2/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 7/7/2021 | GREGORY HOERNER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/8/2021 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 10/12/2021 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 10/13/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 10/13/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 11/12/2021 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/12/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 11/12/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/14/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Rough | 2/14/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 2/14/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 2/14/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 2/14/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 2/14/2022 | Approved | ALAN MORELOS |
| Wood Frame | 2/14/2022 | Approved | ALAN MORELOS |
| Insulation | 2/22/2022 | Approved | RAUL OLAGI |
| Shower Pan | 2/22/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/2/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/2/2022 | Approved | RYAN SALAZAR |
| Final | 4/25/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/25/2022 | Approved | RAUL OLAGI |
| Gas Test | 4/27/2022 | Approved | RAUL OLAGI |
| Final | 1/24/2023 | OK to Issue CofO | RAUL OLAGI |