5418 N SIMPSON AVE 91607
Certificate Information: 5418 N SIMPSON AVE 91607
- Application / Permit
- 21016-20000-10243
- Plan Check / Job No.
- B21VN04803
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | JESSE ARELLANO |
| Corrections Issued | 5/6/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/16/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 8/19/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Issued | 9/14/2021 | APPLICANT |
| CofO in Progress | 5/13/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/17/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | GABRIEL ROBLES |
| Green Code | Cleared | 8/19/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/22/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 10/25/2021 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/29/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/29/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/23/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 11/29/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 12/7/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/7/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/7/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 12/7/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 12/15/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/6/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/10/2022 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 1/10/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/10/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/12/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/12/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 1/12/2022 | Approved | MICHEL ABAJAN |
| Insulation | 1/18/2022 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/24/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/24/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/1/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Wood Construction | 2/3/2022 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 2/7/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/16/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/1/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | THOMAS FINNILA |
| Final | 4/8/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 5/2/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 5/2/2022 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Final | 5/2/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 5/2/2022 | Approved | THOMAS FINNILA |
| Final | 5/12/2022 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 5/12/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | THOMAS FINNILA |