9229 N SEPULVEDA BLVD 91343
Certificate Information: 9229 N SEPULVEDA BLVD 91343
- Application / Permit
- 21016-20000-09910
- Plan Check / Job No.
- B21VN04651
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- RENOVATION OF (E) 125 UNIT 100% AFFORDABLE APT BLDG. REFINISHING OF 111 UNITS. ADD COMMUNICATION SYSTEM TO 5 OF THE 111 REFINISH UNITS. CONVERT 14 UNITS TO MOBILITY UNITS, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- Issued on 11/9/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | CHON CHIO KUO |
| Corrections Issued | 5/24/2021 | CHON CHIO KUO |
| Quality Review Completed | 5/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Plan Check Approved | 11/9/2021 | RARES BODEA |
| Issued | 11/9/2021 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 5/14/2021 | MICHAEL AYERS |
| Fire Marshal Fire Life Safety | Cleared | 7/5/2021 | VIDAL GARCIA |
| Public Housing | Cleared | 10/18/2021 | SUNYOUNG KIM |
| DAS Clearance | Cleared | 10/27/2021 | NORLITO MEDRANO |
Contact Information
| Architect | Mohabir,, Edwin Ramkishore; Lic. No.: C23674 | 25206 BISHOP CT. VALENCIA, CA 91381 |
| Contractor | Precision General Commercial Contractors Inc; Lic. No.: 790153-B | 7250 REDWOOD BLVD STE 214 NOVATO, CA 94945 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 11/19/2021 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/23/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/30/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 1/24/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Insulation | 2/2/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 2/2/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/3/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 3/3/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 3/3/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/4/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/25/2022 | Corrections Issued | DANIEL VARNUM |
| Wood Frame | 3/25/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 3/29/2022 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 3/30/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/30/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/31/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/1/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 4/28/2022 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 5/2/2022 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 5/4/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 5/10/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 6/6/2022 | Conditional Approval | DANIEL VARNUM |
| Wood Frame | 6/21/2022 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 6/23/2022 | Corrections Issued | ANDREW DORSO |
| Drywall Nailing | 6/24/2022 | Partial Inspection | ANDREW DORSO |
| Insulation | 6/24/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 6/24/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/28/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/29/2022 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/29/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/30/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/30/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/1/2022 | Approved | ANDREW DORSO |
| Insulation | 7/12/2022 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 7/15/2022 | Approved | BRUCE CAMPBELL |
| Insulation | 7/21/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 7/21/2022 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 7/25/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 7/27/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/15/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/19/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 9/1/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 9/8/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 9/22/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/5/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/19/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 11/3/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 3/31/2023 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 4/5/2023 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/7/2023 | Partial Inspection | ANDREW DORSO |