8039-8039 1/2 W BLACKBURN AVE 90048

Certificate Information: 8039-8039 1/2 W BLACKBURN AVE 90048

Application / Permit
21016-20000-09854
Plan Check / Job No.
B21VN04614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) DUPLEX TO NEW 2 UNIT DUPLEX W/ATTACHED ADU (ADU ADDRESS is 8039 1/2 W. Blackburn Ave), PER CA GOVT. CODE 65852.2(e)(1)(C)
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 PETER MOSESIAN
Corrections Issued 5/26/2021 PETER MOSESIAN
Quality Review Completed 6/4/2021 OMID HEDAYAT
Plan Check Approved 7/9/2021 PETER MOSESIAN
Issued 7/19/2021 APPLICANT
CofO in Progress 4/26/2022 KENNETH NAGLE
Permit Finaled 4/26/2022 DANIEL ORRANTE
CofO Issued 4/26/2022 DANIEL ORRANTE
Permit Finaled 4/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 6/15/2021 MIGUEL GAMBOA
Address approval Cleared 6/24/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/24/2021 RENZ SORIANO
Sewer availability Cleared 6/24/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 6/28/2021 ISMAEL HERNANDEZ

Contact Information

Architect Podrobinok,, Vadim; Lic. No.: C35693 1344 JACKSON STREET # 107      SAN FRANCISCO, CA 94109
Contractor Romm Builders Inc; Lic. No.: 779702-B 5746 RHODES AVE      VALLEY VILLAGE, CA 91607

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/26/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/26/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 9/3/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 9/3/2021 Approved EVAN COOPER
Green Building Rough 9/3/2021 Not Ready for Inspection EVAN COOPER
HVAC-Rough 9/3/2021 Approved EVAN COOPER
METHANE-Rough 9/3/2021 Approved EVAN COOPER
PLUMBING-Rough 9/3/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 9/17/2021 Approved EVAN COOPER
Green Building Rough 9/17/2021 Approved EVAN COOPER
Insulation 9/17/2021 Approved EVAN COOPER
Interior/Exterior Lathing 9/17/2021 Partial Approval EVAN COOPER
Shower Pan 9/17/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/17/2021 Approved EVAN COOPER
Drywall Nailing 10/1/2021 Approved EVAN COOPER
Interior/Exterior Lathing 10/1/2021 Approved EVAN COOPER
ELECTRICAL-Final 12/23/2021 Approved EVAN COOPER
Final 12/23/2021 Corrections Issued EVAN COOPER
Green Building Final 12/23/2021 Not Ready for Inspection EVAN COOPER
HVAC-Final 12/23/2021 Approved EVAN COOPER
PLUMBING-Final 12/23/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Not Ready EVAN COOPER
Service/Power Release 12/23/2021 Approved EVAN COOPER
Smoke Detectors 12/23/2021 Approved EVAN COOPER
Final 3/10/2022 Corrections Issued EVAN COOPER
Green Building Final 3/10/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved EVAN COOPER
Final 3/14/2022 Corrections Issued EVAN COOPER
Final 4/26/2022 OK to Issue CofO KENNETH NAGLE