8006 N RHODES AVE 91605
Certificate Information: 8006 N RHODES AVE 91605
- Application / Permit
- 21016-20000-09760
- Plan Check / Job No.
- B21VN04593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: CONVERT THE (E) GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | JESSE ARELLANO |
| Corrections Issued | 4/28/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/5/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/19/2021 | JESSE ARELLANO |
| Issued | 6/10/2021 | APPLICANT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| CofO in Progress | 1/29/2024 | MATTHEW NELSON |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| CofO Issued | 3/20/2024 | RUBEN SALAS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Green Code | Cleared | 5/19/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | No Access for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 7/7/2021 | No Access for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 7/12/2021 | Not Ready for Inspection | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/16/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/16/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/29/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 7/29/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/4/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 8/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 8/19/2021 | No Access for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 8/19/2021 | No Access for Inspection | JOHN HAYES |
| Drywall Nailing | 8/23/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/23/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 9/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 9/24/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 9/24/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 10/14/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/2/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/5/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 11/5/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 11/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/5/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/5/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/6/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/19/2023 | OK to Issue CofO | JOHN COLEMAN |