619 S WESTLAKE AVE 90057
Certificate Information: 619 S WESTLAKE AVE 90057
- Application / Permit
- 21016-20000-09621
- Plan Check / Job No.
- B21VN04534
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- 18 NEW PV SOLAR ROOF MOUNTED WATER HEATER SYSTEM
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | PETER MOSESIAN |
| Corrections Issued | 6/13/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Plan Check Approved | 9/30/2021 | PETER MOSESIAN |
| Issued | 12/22/2021 | APPLICANT |
| Permit Finaled | 10/19/2023 | GREGORY POMISH |
Permit Application Clearance Information
| ZA Case | Cleared | 9/10/2021 | DANG NGUYEN |
| ZA Case | Cleared | 9/10/2021 | DANG NGUYEN |
| ZA Case | Cleared | 9/10/2021 | DANG NGUYEN |
| Redevelopment Project Area | Cleared | 9/21/2021 | DAVID URITA |
Contact Information
| Contractor | California Solar Integrators Inc; Lic. No.: 1004246-B | 200S SAN PEDRO ST #500 LOS ANGELES, CA 90012 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/19/2023 | Permit Finaled | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 10/19/2023 | Approved | GREGORY POMISH |