9919-9921 W ROSCOE BLVD 91352
Certificate Information: 9919-9921 W ROSCOE BLVD 91352
- Application / Permit
- 21016-20000-09436
- Plan Check / Job No.
- B21VN04450
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. FIRE SPRINKLERS NFPA-13D
- Permit Issued
- Issued on 9/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/16/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 4/22/2021 | APPLICANT |
| Plan Check Approved | 8/28/2021 | MOHAMMAD ESMAILI |
| Issued | 9/12/2021 | APPLICANT |
| CofO in Progress | 2/2/2022 | GREGG CUMMINGS |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Street Frontage | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 6/15/2021 | KENTON TRINH |
| Distance to fire station | Cleared | 8/6/2021 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 8/6/2021 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 8/28/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Rickmc Construction; Lic. No.: 494953-B | 1267 WILLIS ST REDDING, CA 96001 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/8/2021 | Approved | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 10/8/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/27/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 10/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 10/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 10/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/18/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 11/18/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 11/18/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 11/18/2021 | Corrections Issued | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/1/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 12/1/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 12/1/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 12/1/2021 | Approved | WILLIAM KUEHN |
| Insulation | 12/6/2021 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 12/10/2021 | Corrections Issued | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/10/2021 | Corrections Issued | WILLIAM KUEHN |
| Shower Pan | 12/10/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Drywall Nailing | 12/15/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/15/2021 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 12/15/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 12/22/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | WILLIAM KUEHN |
| Shower Pan | 12/22/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/23/2021 | Partial Approval | WILLIAM KUEHN |
| Gas Test | 1/12/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 1/18/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| Final | 1/27/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| Green Building Rough | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| HVAC-Final | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 1/27/2022 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/31/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 1/31/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/31/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/31/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/31/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 1/31/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/31/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 2/2/2022 | Approved | GREGG CUMMINGS |
| Final | 2/2/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/2/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/2/2022 | Approved | GREGG CUMMINGS |