122 S CRESCENT HEIGHTS BLVD 90048
Certificate Information: 122 S CRESCENT HEIGHTS BLVD 90048
- Application / Permit
- 21016-20000-09434
- Plan Check / Job No.
- B21VN04445
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, NO ADDITION SF AREA. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/10/2022
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | PARISA ZAHABI |
| Corrections Issued | 4/15/2021 | PARISA ZAHABI |
| Issued | 5/3/2021 | APPLICANT |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| Permit Finaled | 1/10/2022 | EVAN COOPER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Livewell Remodeling & Construction; Lic. No.: 1049024-B | 4365 MAMMOTH AVE APT 205 SHERMAN OAKS, CA 91423 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/27/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/27/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/15/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 6/15/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 6/17/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/17/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/24/2021 | Approved | EVAN COOPER |
| Shower Pan | 6/24/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 7/1/2021 | Approved | EVAN COOPER |
| Final | 10/25/2021 | No Access for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 10/25/2021 | No Access for Inspection | EVAN COOPER |
| Final | 12/21/2021 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/21/2021 | Approved | EVAN COOPER |
| Final | 1/10/2022 | Permit Finaled | EVAN COOPER |