5013 N GREENBUSH AVE 91423
Certificate Information: 5013 N GREENBUSH AVE 91423
- Application / Permit
- 21016-20000-09417
- Plan Check / Job No.
- B21VN04432
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) IRR. SHAPE 40' x 18' REC. ROOM AND TWO CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/14/2021
- Issuing Office
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | JEFFREY TANGONAN |
| Corrections Issued | 4/17/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 5/7/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Issued | 5/14/2021 | APPLICANT |
| CofO in Progress | 9/23/2021 | MICHAEL TEMPLE |
| CofO Issued | 10/2/2021 | MICHAEL SMITH |
| Permit Finaled | 10/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/24/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/26/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2021 | Approved | CHARLES POWELL |
| Sewer | 6/15/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/25/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/25/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/2/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/2/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/2/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 7/12/2021 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/12/2021 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/20/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 7/20/2021 | Approved | CHARLES POWELL |
| Final | 9/17/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 9/17/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 9/17/2021 | Approved | MICHAEL TEMPLE |
| Final | 9/23/2021 | Conditional Approval | MICHAEL TEMPLE |
| Final | 9/23/2021 | OK to Issue CofO | MICHAEL TEMPLE |