1633 S ABBOT KINNEY BLVD 90291

Certificate Information: 1633 S ABBOT KINNEY BLVD 90291

Application / Permit
21016-20000-09315
Plan Check / Job No.
B21VN04393
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
FIRE DAMAGED REPAIR TO (E) RESTAURANT, UPGRADE TO 2-HR FIRE CONSTR ON EXTERIOR WALL ONLY . no change on floor area, & building height .
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 7/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 CHON CHIO KUO
Corrections Issued 5/24/2021 CHON CHIO KUO
Quality Review Completed 5/27/2021 STEVEN KIM
Building Plans Picked Up 6/1/2021 APPLICANT
Applicant returned to address corrections 8/6/2021 RARES BODEA
Plan Check Approved 10/28/2021 RARES BODEA
Issued 1/18/2022 APPLICANT
CofO in Progress 6/18/2025 FARHAD DADBIN
Permit Finaled 7/2/2025 DAVID TSAU
CofO Issued 7/2/2025 DAVID TSAU
Permit Finaled 7/2/2025 DAVID TSAU

Permit Application Clearance Information

Coastal Zone Cleared 7/9/2021 NOAH MCCOY
ZA Case Cleared 7/9/2021 NOAH MCCOY
ZA Case Cleared 7/9/2021 NOAH MCCOY
ZA Case Cleared 7/9/2021 NOAH MCCOY
ZA Case Cleared 7/9/2021 NOAH MCCOY
ZI Cleared 7/9/2021 BINDU KANNAN
Eng Process Fee Ord 176,300 Cleared 7/23/2021 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 7/23/2021 NIKTA MOUSAVI
DAS Clearance Cleared 9/28/2021 CHON CHIO KUO

Contact Information

Contractor Clc Builders Inc; Lic. No.: 580175-B 22916 ELKWOOD STREET      WEST HILLS, CA 91304

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/8/2022 Partial Approval JOHN DODGE
Wood Frame 3/17/2022 Partial Approval JOHN DODGE
Insulation 3/24/2022 Partial Approval NICK LAROCCA
Drywall Nailing 4/8/2022 Approved JOHN DODGE
Light Gage Steel Frame 8/1/2022 Partial Approval SORIN CIRSTOIU
Insulation 8/4/2022 Partial Approval NICK LAROCCA
Drywall Nailing 8/9/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 8/9/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 8/12/2022 Approved SORIN CIRSTOIU
Final 1/18/2023 Corrections Issued SORIN CIRSTOIU
Reinforced Masonry Frame 1/18/2023 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 1/18/2023 Approved SORIN CIRSTOIU
Insulation 12/13/2023 Not Ready for Inspection FARHAD DADBIN
Wood Frame 12/13/2023 Not Ready for Inspection FARHAD DADBIN
Insulation 1/10/2024 Partial Approval FARHAD DADBIN
Wood Frame 1/10/2024 Partial Approval FARHAD DADBIN
Drywall Nailing 1/17/2024 Partial Approval FARHAD DADBIN
Insulation 2/23/2024 Not Ready for Inspection FARHAD DADBIN
Insulation 5/8/2024 Partial Approval FARHAD DADBIN
Drywall Nailing 5/10/2024 Partial Approval RICARDO ROBLES
Interior/Exterior Lathing 2/26/2025 Approved FARHAD DADBIN
Final 6/12/2025 OK to Issue CofO FARHAD DADBIN
Reinforced Masonry Frame 6/12/2025 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved FARHAD DADBIN