12650-12652 W CUMPSTON ST 91607
Certificate Information: 12650-12652 W CUMPSTON ST 91607
- Application / Permit
- 21016-20000-09260
- Plan Check / Job No.
- B21VN04376
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 17'-6" X 24' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) AND REMODEL (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 6/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/19/2021 | RAPHAEL ROSAS |
| Issued | 9/3/2021 | APPLICANT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| CofO in Progress | 6/13/2025 | RAUL OLAGI |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
| CofO Issued | 6/18/2025 | RUBEN SALAS |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/16/2021 | GABRIEL ROBLES |
| Specific Plan | Cleared | 6/29/2021 | ANDREW JORGENSEN |
| ZI | Cleared | 6/29/2021 | ANDREW JORGENSEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 9/24/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/29/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 11/3/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/10/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/15/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 12/28/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| HVAC-Rough | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 7/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| HVAC-Rough | 7/21/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 7/21/2022 | Approved | RAFAEL CORTES |
| Wood Frame | 7/21/2022 | Partial Approval | RAFAEL CORTES |
| ELECTRICAL-Rough | 9/1/2022 | Corrections Issued | ALAN MORELOS |
| HVAC-Rough | 9/1/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 10/3/2022 | Corrections Issued | RAFAEL CORTES |
| ELECTRICAL-Rough | 11/2/2022 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 11/10/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 11/10/2022 | Corrections Issued | CALEB MEISTER |
| Wood Frame | 11/10/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 11/18/2022 | Partial Approval | WILLIAM WREN |
| Wood Frame | 11/18/2022 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 12/2/2022 | Approved | KIRK SANDERS |
| HVAC-Rough | 12/2/2022 | Approved | KIRK SANDERS |
| Wood Frame | 12/2/2022 | Approved | KIRK SANDERS |
| Insulation | 12/9/2022 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/22/2022 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/22/2022 | Approved | KIRK SANDERS |
| Shower Pan | 2/3/2023 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 2/3/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | KIRK SANDERS |
| Shower Pan | 2/8/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 2/21/2023 | Approved | JUAN VALENZUELA |
| Pre-Inspection | 8/28/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | KIRK SANDERS |
| Final | 12/19/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 12/19/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 12/19/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 4/10/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/10/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/10/2024 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/12/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 4/12/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 7/29/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 8/16/2024 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/20/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 8/27/2024 | Approved | ROBERT GOLD |
| Final | 8/27/2024 | Corrections Issued | ROBERT GOLD |
| Final | 2/21/2025 | Partial Approval | ROBERT GOLD |
| Green Building Final | 2/21/2025 | Approved | ROBERT GOLD |
| HVAC-Final | 2/21/2025 | Approved | ROBERT GOLD |
| PLUMBING-Final | 2/21/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 2/21/2025 | Approved | ROBERT GOLD |
| Final | 6/13/2025 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 6/13/2025 | Approved | RAUL OLAGI |