8388-8390 N SEDAN AVE 91304
Certificate Information: 8388-8390 N SEDAN AVE 91304
- Application / Permit
- 21016-20000-09150
- Plan Check / Job No.
- B21VN04334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 350 SF PORTION OF 1ST STORY AND 581 SF 2ND STORY OF (E) SFD TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/18/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/28/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Issued | 12/20/2021 | APPLICANT |
| CofO in Progress | 12/22/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 1/5/2023 | JOHN JANSON |
| CofO Issued | 1/5/2023 | JOHN JANSON |
| Permit Finaled | 1/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/29/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 7/28/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Saban Global Incorporated; Lic. No.: 912915-B | P O BOX 57544 SHERMAN OAKS, CA 91403 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 2/1/2022 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 2/1/2022 | Approved | DAVID SCANTLIN |
| Sewer | 2/1/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 2/10/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/10/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 2/10/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/1/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/1/2022 | Approved | DAVID SCANTLIN |
| Insulation | 3/1/2022 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 3/7/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/23/2022 | Approved | JESUS PINEDA |
| Shower Pan | 3/23/2022 | Approved | JESUS PINEDA |
| Final | 7/13/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/13/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/13/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 11/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 11/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 12/21/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/21/2022 | Approved | CHRIS CHRISTENSEN |