8388-8390 N SEDAN AVE 91304

Certificate Information: 8388-8390 N SEDAN AVE 91304

Application / Permit
21016-20000-09150
Plan Check / Job No.
B21VN04334
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 350 SF PORTION OF 1ST STORY AND 581 SF 2ND STORY OF (E) SFD TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/20/2021
Issuing Office
Current Status
CofO Issued on 1/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/16/2021 RAPHAEL ROSAS
Corrections Issued 4/18/2021 RAPHAEL ROSAS
Plan Check Approved 7/28/2021 RAPHAEL ROSAS
Building Plans Picked Up 7/29/2021 APPLICANT
Issued 12/20/2021 APPLICANT
CofO in Progress 12/22/2022 CHRIS CHRISTENSEN
Permit Finaled 1/5/2023 JOHN JANSON
CofO Issued 1/5/2023 JOHN JANSON
Permit Finaled 1/5/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/29/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/29/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 7/28/2021 RAPHAEL ROSAS

Contact Information

Contractor Saban Global Incorporated; Lic. No.: 912915-B P O BOX 57544      SHERMAN OAKS, CA 91403
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 2/1/2022 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 2/1/2022 Approved DAVID SCANTLIN
Sewer 2/1/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/10/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 2/10/2022 Approved DAVID SCANTLIN
Green Building Rough 2/10/2022 Approved DAVID SCANTLIN
HVAC-Rough 2/10/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/1/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/1/2022 Approved DAVID SCANTLIN
HVAC-Rough 3/1/2022 Approved DAVID SCANTLIN
Insulation 3/1/2022 Approved DAVID SCANTLIN
Drywall Nailing 3/7/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 3/23/2022 Approved JESUS PINEDA
Shower Pan 3/23/2022 Approved JESUS PINEDA
Final 7/13/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/13/2022 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 7/13/2022 Approved CHRIS CHRISTENSEN
Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/22/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved CHRIS CHRISTENSEN
Final 12/21/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 12/21/2022 Approved CHRIS CHRISTENSEN