9759-9761 N KESSLER AVE 91311
Certificate Information: 9759-9761 N KESSLER AVE 91311
- Application / Permit
- 21016-20000-08939
- Plan Check / Job No.
- B21VN04233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) IN (E) SINGLE FAMILY DWELLING. CONVERT 9' X 8'-6" PORTION OF GARAGE TO LAUNDRY FOR SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/16/2021
- Issuing Office
- Current Status
- CofO Issued on 4/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | SERGIO MUNIZ |
| Corrections Issued | 5/15/2021 | SERGIO MUNIZ |
| Plan Check Approved | 6/14/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| Issued | 7/16/2021 | APPLICANT |
| CofO in Progress | 4/23/2022 | JEFFREY PARD |
| Permit Finaled | 4/26/2022 | JOHN JANSON |
| CofO Issued | 4/26/2022 | JOHN JANSON |
| Permit Finaled | 4/26/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/3/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 16200 VENTURA BLVD STE 317 ENCINO, CA 91436 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD STE 317 ENCINO, CA 91436 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/2/2021 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 8/9/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 8/9/2021 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 8/16/2021 | Not Ready for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 8/16/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/16/2021 | Not Ready for Inspection | JEFFREY PARD |
| Deputy Drilled-In Anchors | 8/27/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 8/27/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/27/2021 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 9/15/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/21/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 9/21/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/29/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 9/29/2021 | Not Ready for Inspection | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 9/29/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 10/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 10/7/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 10/14/2021 | Not Ready for Inspection | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 10/14/2021 | Approved | JEFFREY PARD |
| Insulation | 10/19/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 10/21/2021 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 10/25/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/25/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 11/16/2021 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/4/2022 | Approved | JEFFREY PARD |
| Final | 2/4/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 2/4/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 2/4/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 2/4/2022 | Approved | JEFFREY PARD |
| Final | 4/21/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 4/21/2022 | Approved | JEFFREY PARD |