6701 N ODESSA AVE 91406
Certificate Information: 6701 N ODESSA AVE 91406
- Application / Permit
- 21016-20000-08841
- Plan Check / Job No.
- B21VN04199
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- TENANT IMPROVEMENT TO (E) COMMERCIAL BLDG AND CHANGE THE USE OF A PORTION OF THE (E) OFFICE AREA TO A WAREHOUSE AND RESTRIPE PARKING LOT
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | MARVEL DELACRUZ |
| Corrections Issued | 4/18/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 4/23/2021 | STEVEN KIM |
| Applicant returned to address corrections | 8/11/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 8/13/2021 | MARVEL DELACRUZ |
| Issued | 5/3/2022 | APPLICANT |
| CofO in Progress | 11/23/2022 | CAMERON CHABAN |
| CofO Issued | 12/1/2022 | JEFFREY DURAN |
| Permit Finaled | 12/1/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/10/2021 | LEE GUILBEAUX |
| Green Code | Cleared | 6/15/2021 | MICHAEL AYERS |
| DAS Clearance | Cleared | 7/13/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Riat Construction Inc; Lic. No.: 956809-B | P O BOX 129 RANCHO CUCAMONGA, CA 91739 |
| Engineer | Nagarajan,, Sivaram; Lic. No.: S6349 | 167 MATISSE CIRCLE ALISO VIEJO, CA 92656 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2022 | Corrections Issued | CAMERON CHABAN |
| Footing/Foundation/Slab | 6/9/2022 | Approved | CAMERON CHABAN |
| Wood Frame | 6/17/2022 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 6/23/2022 | Conditional Approval | CAMERON CHABAN |
| Insulation | 7/1/2022 | Approved | CAMERON CHABAN |
| Footing/Foundation/Slab | 7/6/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 7/11/2022 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 7/14/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Wood Frame | 8/3/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 8/8/2022 | Approved | ANDREW DORSO |
| Partition/T-Bar Ceiling | 8/25/2022 | Corrections Issued | CAMERON CHABAN |
| Partition/T-Bar Ceiling | 8/31/2022 | Approved | CAMERON CHABAN |
| Final | 11/10/2022 | Corrections Issued | CAMERON CHABAN |
| Green Building Final | 11/10/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Rough | 11/10/2022 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 11/10/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 11/10/2022 | Approved | CAMERON CHABAN |
| Final | 11/22/2022 | OK to Issue CofO | CAMERON CHABAN |
| Green Building Final | 11/22/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | CAMERON CHABAN |