22553 W SATICOY ST 91307
Certificate Information: 22553 W SATICOY ST 91307
- Application / Permit
- 21016-20000-08688
- Plan Check / Job No.
- B21VN04143
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20'6" X 20'6" DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); ALL WORK PER WFPP
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | SEAN SHAHMIRI |
| Corrections Issued | 4/14/2021 | SEAN SHAHMIRI |
| Building Plans Picked Up | 4/14/2021 | APPLICANT |
| Applicant returned to address corrections | 6/14/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/23/2021 | SEAN SHAHMIRI |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 7/26/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/29/2022 | JOHN JANSON |
| CofO Issued | 7/29/2022 | JOHN JANSON |
| Permit Finaled | 7/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 9/21/2021 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 10/19/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/19/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 11/22/2021 | Corrections Issued | JEFFREY PARD |
| Sewer | 12/7/2021 | Partial Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/14/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 12/14/2021 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 12/28/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 2/10/2022 | Corrections Issued | JEFFREY PARD |
| Wood Frame | 2/10/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 2/17/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/17/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 2/24/2022 | Approved | JEFFREY PARD |
| Wood Frame | 2/24/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/8/2022 | Approved | JESUS PINEDA |
| Final | 6/8/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/8/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/8/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 6/28/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 6/28/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 6/28/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/28/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 6/28/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 7/5/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 7/5/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 7/25/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/25/2022 | Approved | CHRIS CHRISTENSEN |