2248 S HOBART BLVD 90018

Certificate Information: 2248 S HOBART BLVD 90018

Application / Permit
21016-20000-08578
Plan Check / Job No.
B21VN04094
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ALTERATIONS TO CREATE THREE NEW BATHROOM, AND REMODEL THE (E) BATHROOM, REMODEL THE (E) KITCHEN, AND CREATE A NEW LAUNDRY ROOM AND ONE NEW WET BAR.
Permit Issued
Issued on 5/4/2021
Issuing Office
Current Status
Permit Finaled on 11/30/2021

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/12/2021 COLIN LOREDO
Corrections Issued 4/15/2021 COLIN LOREDO
Plan Check Approved 5/4/2021 COLIN LOREDO
Issued 5/4/2021 APPLICANT
Building Plans Picked Up 5/4/2021 APPLICANT
Permit Finaled 11/30/2021 ENRIQUE PREZA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jiwon; Lic. No.: C89281 3466 BONITA AVE      SANTA CLARA, CA 95051

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/29/2021 Approved ENRIQUE PREZA
HVAC-Rough 6/29/2021 Approved ENRIQUE PREZA
PLUMBING-Rough 6/29/2021 Approved ENRIQUE PREZA
Insulation 7/9/2021 Approved ENRIQUE PREZA
Drywall Nailing 7/16/2021 Approved ENRIQUE PREZA
Shower Pan 7/16/2021 Approved ENRIQUE PREZA
Wood Frame 8/4/2021 Approved ENRIQUE PREZA
Footing/Foundation/Slab 8/12/2021 Approved ENRIQUE PREZA
BUILDING-Rough-Frame 10/19/2021 Partial Approval ENRIQUE PREZA
ELECTRICAL-Final 10/19/2021 Not Ready for Inspection ENRIQUE PREZA
Final 10/19/2021 Not Ready for Inspection ENRIQUE PREZA
HVAC-Final 10/19/2021 Not Ready for Inspection ENRIQUE PREZA
MERV13>=Final 10/19/2021 Not Ready for Inspection ENRIQUE PREZA
MERV13>=Rough 10/19/2021 Corrections Issued ENRIQUE PREZA
PLUMBING-Final 10/19/2021 Not Ready for Inspection ENRIQUE PREZA
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Not Ready ENRIQUE PREZA
Smoke Detectors 10/19/2021 Approved ENRIQUE PREZA
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Not Ready DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Not Ready DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready DANIEL GONZALEZ
BUILDING-Rough-Frame 11/9/2021 Approved ENRIQUE PREZA
Final 11/9/2021 Corrections Issued ENRIQUE PREZA
MERV13>=Final 11/9/2021 Not Ready for Inspection ENRIQUE PREZA
MERV13>=Rough 11/9/2021 Approved ENRIQUE PREZA
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV Approved ENRIQUE PREZA
Final 11/22/2021 Corrections Issued ENRIQUE PREZA
MERV13>=Final 11/22/2021 Corrections Issued ENRIQUE PREZA
Final 11/30/2021 Permit Finaled ENRIQUE PREZA
MERV13>=Final 11/30/2021 Approved ENRIQUE PREZA