23138 W BALTAR ST 91304

Certificate Information: 23138 W BALTAR ST 91304

Application / Permit
21016-20000-08552
Plan Check / Job No.
B21VN04082
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRE DAMAGE REPAIRES TO THE (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. REPLACE ROOF STRUCTURE, REFRAME PARTIAL WALLS, REPLACE EXTERIOR WALLS, DRYWALL AND FINISHES. REPLACE ALL WINDOWS AND DOORS, REWIRE AND REPLACE PLUMBING AND ELECTRICAL WHERE NEEDED.
Permit Issued
Issued on 6/11/2021
Issuing Office
Current Status
Permit Finaled on 4/27/2022

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 SARKIS HARABEDIAN
Corrections Issued 4/14/2021 SARKIS HARABEDIAN
Plan Check Approved 6/10/2021 SARKIS HARABEDIAN
Issued 6/11/2021 APPLICANT
Building Plans Picked Up 6/11/2021 APPLICANT
Permit Finaled 4/26/2022 CHRIS CHRISTENSEN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Mc George Construction Ii Inc; Lic. No.: 797933-B 801 MITCHELL RD #104      NEWBURY PARK, CA 91320
Engineer Runyan,, William Robert; Lic. No.: C32138 10213 HEATHER ST      ALTA LOMA, CA 91737

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 6/28/2021 Approved DAVID STEPANYAN
Deputy Reinf. Concrete 6/29/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 1/6/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 1/11/2022 No Access for Inspection PETER FOLLING
HVAC-Rough 1/11/2022 No Access for Inspection PETER FOLLING
PLUMBING-Rough 1/11/2022 No Access for Inspection PETER FOLLING
BUILDING-Rough-Frame 1/13/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 1/13/2022 Approved JUSTIN HAWLEY
Green Building Rough 1/13/2022 Approved JUSTIN HAWLEY
HVAC-Rough 1/13/2022 Approved JUSTIN HAWLEY
PLUMBING-Rough 1/13/2022 Approved JUSTIN HAWLEY
Insulation 1/19/2022 Approved JAVIER RAMOS JR
Drywall Nailing 1/27/2022 Approved DAVID SCANTLIN
Gas Test 3/7/2022 Approved JUSTIN HAWLEY
Shower Pan 3/7/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 3/11/2022 Approved JESUS PINEDA
Final 4/20/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/20/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 4/20/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 4/20/2022 Approved CHRIS CHRISTENSEN
Final 4/26/2022 Permit Finaled CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Approved CHRIS CHRISTENSEN