1020 E INDIANA AVE 90291

Certificate Information: 1020 E INDIANA AVE 90291

Application / Permit
21016-20000-08549
Plan Check / Job No.
B21VN04077
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PARTIAL REMODEL TO THE (E) KITCHEN, MASTER BEDROOM AND BATHROOM INCLUDING ADDITION OF NEW WINDOWS AND DOORS AND PARTITION WALLS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
Permit Finaled on 5/26/2022

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 OMAR GARNICA
Corrections Issued 4/8/2021 OMAR GARNICA
Plan Check Approved 4/19/2021 OMAR GARNICA
Issued 4/19/2021 APPLICANT
Building Plans Picked Up 4/20/2021 APPLICANT
Permit Finaled 5/26/2022 JESUS RODRIGUEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Dreamcatcher Remodeling; Lic. No.: 1036088-B 14823 1/4 OXNARD ST      VAN NUYS, CA 91411
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2021 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 5/5/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 5/6/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 6/25/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/25/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/7/2021 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 7/16/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/4/2021 Approved PIERRE VEGA
HVAC-Rough 8/11/2021 Approved JOHNNY MIRANDA
Insulation 8/11/2021 Approved JOHNNY MIRANDA
Drywall Nailing 9/3/2021 Corrections Issued SHAVONNE ESPINOZA
Shower Pan 9/3/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 9/8/2021 Approved JAVIER RAMOS JR
Shower Pan 9/15/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/6/2021 Partial Approval RICHARD STEINBACH
Final 2/16/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 2/16/2022 Corrections Issued DAVID FEILER
Final 5/26/2022 Permit Finaled JESUS RODRIGUEZ
Smoke Detectors 5/26/2022 Approved JESUS RODRIGUEZ