538 W 111TH PL 90044

Certificate Information: 538 W 111TH PL 90044

Application / Permit
21016-20000-08476
Plan Check / Job No.
B21VN04032
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE (18'-0" x 20'-2"),408.54 SQFT INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/2/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 PETER MOSESIAN
Corrections Issued 4/16/2021 PETER MOSESIAN
Building Plans Picked Up 4/23/2021 APPLICANT
Plan Check Approved 3/23/2022 PETER MOSESIAN
Issued 1/2/2025 APPLICANT
CofO in Progress 6/23/2025 ANSON MAGLASANG
CofO Issued 6/23/2025 ANSON MAGLASANG
Permit Finaled 6/23/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/12/2021 ROSA SILVA
Sewer availability Cleared 5/12/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 5/13/2021 ROSA SILVA
Construction near power lines Cleared 9/21/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/17/2025 Approved BEN MOLSTAD
ELECTRICAL-Rough 1/17/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 1/17/2025 Corrections Issued BEN MOLSTAD
Wood Frame 1/17/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 1/22/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/22/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 1/27/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval BEN MOLSTAD
PLUMBING-Rough 1/27/2025 Approved BEN MOLSTAD
Underground Mechanical 1/27/2025 Approved BEN MOLSTAD
Wood Frame 1/27/2025 Approved BEN MOLSTAD
Insulation 1/30/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Approved BEN MOLSTAD
Green Building Rough 2/7/2025 Approved BEN MOLSTAD
Drywall Nailing 2/11/2025 Partial Approval BEN MOLSTAD
Drywall Nailing 2/14/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 3/5/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 3/5/2025 Corrections Issued BEN MOLSTAD
Final 3/5/2025 Corrections Issued BEN MOLSTAD
Green Building Final 3/5/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Approved BEN MOLSTAD
Smoke Detectors 3/5/2025 Corrections Issued BEN MOLSTAD
Final 3/7/2025 Corrections Issued BEN MOLSTAD
Green Building Final 3/7/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 3/7/2025 Not Ready for Inspection BEN MOLSTAD
Final 3/12/2025 Corrections Issued BEN MOLSTAD
Green Building Final 3/12/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 3/12/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 6/20/2025 Approved BEN MOLSTAD
Final 6/20/2025 OK to Issue CofO BEN MOLSTAD
Green Building Final 6/20/2025 Approved BEN MOLSTAD
HVAC-Final 6/20/2025 Approved BEN MOLSTAD
PLUMBING-Final 6/20/2025 Approved BEN MOLSTAD
Smoke Detectors 6/20/2025 Approved BEN MOLSTAD