6108 3/4 S 10TH AVE 90043

Certificate Information: 6108 3/4 S 10TH AVE 90043

Application / Permit
21016-20000-08471
Plan Check / Job No.
B21VN04027
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18'-4" X 18'-7" PORTION OF EXISTING DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
CofO Issued on 4/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/9/2021 RAPHAEL ROSAS
Corrections Issued 4/10/2021 RAPHAEL ROSAS
Issued 9/2/2021 APPLICANT
Building Plans Picked Up 9/7/2021 APPLICANT
CofO in Progress 4/11/2022 ENRIQUE MIRELES
CofO in Progress 4/11/2022 ENRIQUE MIRELES
Permit Finaled 4/15/2022 DEROLD HAUFF
CofO Issued 4/15/2022 DEROLD HAUFF
Permit Finaled 4/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/21/2021 RENZ SORIANO
Sewer availability Cleared 4/21/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/22/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 5/10/2021 MICHAEL SOTO
Construction near power lines Cleared 8/21/2021 RIDWAN HARDY

Contact Information

Contractor E G N Builders Group; Lic. No.: 1051430-B 5000 PARKWAY CALABASAS   SUITE 308    CALABASAS, CA 91302
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/4/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/6/2021 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/8/2021 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/13/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 10/13/2021 Corrections Issued FREDDIE RIVERA
Sewer 10/18/2021 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 12/10/2021 Partial Approval ANTHONY EGSON
Insulation 12/17/2021 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 12/17/2021 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 12/27/2021 Corrections Issued HORACE FULTZ
Green Building Rough 12/27/2021 Not Ready for Inspection HORACE FULTZ
Wood Frame 12/27/2021 Not Ready for Inspection HORACE FULTZ
BUILDING-Rough-Frame 2/3/2022 Approved FREDDIE RIVERA
Green Building Rough 2/3/2022 Approved FREDDIE RIVERA
Insulation 2/3/2022 Approved FREDDIE RIVERA
Drywall Nailing 2/14/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 2/14/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 2/17/2022 Partial Approval LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Not Ready ENRIQUE MIRELES
Gas Test 3/15/2022 Approved ENRIQUE MIRELES
Final 3/21/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/21/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/21/2022 Approved ENRIQUE MIRELES
Final 3/29/2022 Corrections Issued ENRIQUE MIRELES
Final 4/4/2022 Corrections Issued ENRIQUE MIRELES
Final 4/8/2022 OK to Issue CofO ENRIQUE MIRELES