5940 N LINDLEY AVE 91316

Certificate Information: 5940 N LINDLEY AVE 91316

Application / Permit
21016-20000-08405
Plan Check / Job No.
B21VN03985
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) 10' X 19' ATTACHED 1 -CAR GARAGE INTO A (N) BEDROOM AND BATHROOM FOR THE (E) SFD. SEE COMMENTS.
Permit Issued
Issued on 7/7/2021
Issuing Office
Current Status
CofO Issued on 8/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 ANGELICA DAVE
Corrections Issued 4/7/2021 ANGELICA DAVE
Applicant returned to address corrections 4/21/2021 ANGELICA DAVE
Applicant returned to address corrections 5/7/2021 ANGELICA DAVE
Applicant returned to address corrections 5/19/2021 ANGELICA DAVE
Plan Check Approved 7/2/2021 ANGELICA MARTINEZ
Issued 7/7/2021 APPLICANT
Building Plans Picked Up 7/8/2021 APPLICANT
CofO in Progress 8/13/2021 STEVEN BACK
CofO Issued 8/17/2021 MICHAEL SMITH
Permit Finaled 8/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/14/2021 ADRIAN CASTRO
Sewer availability Cleared 5/14/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Beizai,, Vahid Vic; Lic. No.: C43801 1125 EAST BROADWAY 159      GLENDALE, CA 91025

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/12/2021 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 7/12/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 7/12/2021 Corrections Issued STEVEN BACK
Pre-Inspection 7/12/2021 Partial Inspection STEVEN BACK
BUILDING-Rough-Frame 7/14/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 7/14/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 7/14/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 7/23/2021 Corrections Issued STEVEN BACK
Final 7/23/2021 Not Ready for Inspection STEVEN BACK
Green Building Final 7/23/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 7/23/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 7/23/2021 Approved STEVEN BACK
Footing/Foundation/Slab 8/5/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 8/9/2021 Approved STEVEN BACK
ELECTRICAL-Rough 8/9/2021 Approved STEVEN BACK
Green Building Rough 8/9/2021 Approved STEVEN BACK
HVAC-Rough 8/9/2021 Approved STEVEN BACK
Interior/Exterior Lathing 8/9/2021 Partial Approval STEVEN BACK
Interior/Exterior Lathing 8/11/2021 Approved ASHLEY THOMPSON
Final 8/13/2021 OK to Issue CofO STEVEN BACK
Green Building Final 8/13/2021 Approved STEVEN BACK
Insulation 8/13/2021 Approved STEVEN BACK
Interior/Exterior Lathing 8/13/2021 Approved STEVEN BACK