23057 W VANOWEN ST 91307

Certificate Information: 23057 W VANOWEN ST 91307

Application / Permit
21016-20000-08379
Plan Check / Job No.
B21VN03969
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 21' DETACHED 2-CAR GARAGE TO ADU PER GCS65852.2(e)(1)(A). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 9/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 GURUNATH NESARAJAH
Corrections Issued 4/7/2021 GURUNATH NESARAJAH
Building Plans Picked Up 4/8/2021 APPLICANT
Plan Check Approved 4/18/2021 GURUNATH NESARAJAH
Issued 4/19/2021 APPLICANT
CofO in Progress 12/7/2021 TROY SANDERS
Permit Finaled 9/13/2022 DANIEL ORRANTE
CofO Issued 9/13/2022 DANIEL ORRANTE
Permit Finaled 9/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/9/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/9/2021 LEE GUILBEAUX
Sewer availability Cleared 4/9/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/9/2021 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor My Home Builders Inc; Lic. No.: 1002927-B 20720 VENTURA BLVD #280      WOODLAND HILLS, CA 91364

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/26/2021 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/3/2021 Approved TROY SANDERS
Footing/Foundation/Slab 6/3/2021 Approved TROY SANDERS
Sewer 6/3/2021 Approved TROY SANDERS
Underground Mechanical 6/3/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 7/8/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 7/8/2021 Approved TROY SANDERS
Green Building Rough 7/8/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 7/8/2021 Approved TROY SANDERS
Insulation 7/8/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 7/8/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 8/5/2021 Approved TROY SANDERS
Green Building Rough 8/5/2021 Approved TROY SANDERS
Insulation 8/5/2021 Approved TROY SANDERS
Interior/Exterior Lathing 8/5/2021 Approved TROY SANDERS
Shower Pan 8/5/2021 Approved TROY SANDERS
Drywall Nailing 8/9/2021 Approved STEPHANIE SWANSON
ELECTRICAL-Final 12/6/2021 Approved TROY SANDERS
Final 12/6/2021 OK to Issue CofO TROY SANDERS
Green Building Final 12/6/2021 Approved TROY SANDERS
HVAC-Final 12/6/2021 Approved TROY SANDERS
PLUMBING-Final 12/6/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Approved TROY SANDERS