16309 W LASSEN ST 91343
Certificate Information: 16309 W LASSEN ST 91343
- Application / Permit
- 21016-20000-08286
- Plan Check / Job No.
- B21VN03901
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 21' X 21' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/30/2021
- Issuing Office
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 4/11/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/28/2021 | GURUNATH NESARAJAH |
| Issued | 5/30/2021 | APPLICANT |
| Building Plans Picked Up | 6/3/2021 | APPLICANT |
| CofO in Progress | 3/15/2023 | JAVIER RAMOS JR |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
| CofO Issued | 4/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/15/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 5/17/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/23/2021 | Conditional Approval | MARK JOHNSON |
| PLUMBING-Rough | 9/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/29/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 9/29/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 10/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 10/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 10/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/5/2022 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 7/5/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/12/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/12/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/19/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 8/19/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/19/2022 | Conditional Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 9/29/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/29/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/18/2022 | Approved | JAVIER RAMOS JR |
| Final | 1/13/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 1/13/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/13/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 2/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/10/2023 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/10/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/15/2023 | OK to Issue CofO | JAVIER RAMOS JR |