11314 N MONTGOMERY AVE 91344

Certificate Information: 11314 N MONTGOMERY AVE 91344

Application / Permit
21016-20000-08257
Plan Check / Job No.
B21VN03881
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 11' X 25'-6" PATIO COVER AND ADD 11' X 25'-6" FOR (N) KITCHEN, DINING AND LAUNDRY ROOM. CONVERT (E) KITCHEN TO BEDROOM, AND BATHROOM. NEW DOORS AND WINDOWS. ALL WORK PER WFPP.
Permit Issued
Issued on 5/26/2021
Issuing Office
Valley
Current Status
Issued on 5/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 RAPHAEL ROSAS
Corrections Issued 4/7/2021 RAPHAEL ROSAS
Plan Check Approved 5/9/2021 RAPHAEL ROSAS
Building Plans Picked Up 5/11/2021 APPLICANT
Issued 5/26/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/14/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 4/14/2021 GABRIEL ROBLES
Sewer availability Cleared 4/14/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 4/21/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/14/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 6/14/2021 Partial Approval MARK JOHNSON
Pre-Inspection 6/14/2021 Partial Inspection MARK JOHNSON
ELECTRICAL-Rough 6/28/2021 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 6/28/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Partial Approval JOHN HAYES
Wood Frame 7/12/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 7/20/2021 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 7/20/2021 Partial Approval DAVID SCANTLIN
Insulation 8/3/2021 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 8/3/2021 Partial Approval LILIANA PORTILLO
Insulation 8/5/2021 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 8/9/2021 Partial Approval AMY COLIN
HVAC-Rough 8/9/2021 Partial Approval AMY COLIN
Drywall Nailing 8/16/2021 Partial Approval ADAM ESCOTO
PLUMBING-Rough 11/17/2021 Partial Approval WILLIAM KUEHN
Footing/Foundation/Slab 12/3/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 12/21/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 12/21/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 12/28/2021 Corrections Issued BRENDAN LOONEY
Insulation 12/28/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 12/29/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 12/29/2021 Approved MICHEL ABAJAN
HVAC-Rough 12/29/2021 Approved MICHEL ABAJAN
Insulation 12/29/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/4/2022 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Approved MARK JOHNSON
Insulation 1/19/2022 Approved MICHAEL TEMPLE
Drywall Nailing 1/31/2022 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 5/2/2022 Approved DEANDRE HOFFMAN
Shower Pan 5/2/2022 Approved DEANDRE HOFFMAN