5079 N DON PIO DR 91364

Certificate Information: 5079 N DON PIO DR 91364

Application / Permit
21016-20000-08235
Plan Check / Job No.
B21VN03866
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852(e)(1)(A)
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 LUISANGEL VALENZUELA
Corrections Issued 5/6/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/27/2021 LUISANGEL VALENZUELA
Plan Check Approved 11/16/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 12/22/2021 APPLICANT
Issued 1/14/2022 APPLICANT
CofO in Progress 8/21/2023 JOHN KIDWELL
Permit Finaled 8/22/2023 JOHN JANSON
CofO Issued 8/22/2023 JOHN JANSON
Permit Finaled 8/22/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/4/2021 CARLOS AGUILERA
Sewer availability Cleared 10/4/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/5/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/11/2022 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/19/2023 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 7/19/2023 Corrections Issued PETER FOLLING
Final 7/19/2023 Corrections Issued PETER FOLLING
Green Building Rough 7/19/2023 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 7/19/2023 Corrections Issued PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Not Ready PETER FOLLING
Final 8/3/2023 Corrections Issued JOHN KIDWELL
BUILDING-Rough-Frame 8/21/2023 Approved JOHN KIDWELL
Final 8/21/2023 OK to Issue CofO JOHN KIDWELL
Green Building Final 8/21/2023 Approved JOHN KIDWELL
Green Building Rough 8/21/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/21/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 8/21/2023 Approved JOHN KIDWELL