4357 1/2 N FARMDALE AVE 91604
Certificate Information: 4357 1/2 N FARMDALE AVE 91604
- Application / Permit
- 21016-20000-08230
- Plan Check / Job No.
- B21VN03860
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 18' (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/7/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/9/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/10/2021 | APPLICANT |
| Issued | 9/21/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | THOMAS FINNILA |
| CofO Issued | 8/30/2022 | MICHAEL SMITH |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 7/13/2021 | RIDWAN HARDY |
| ZI | Cleared | 8/3/2021 | TERRI OSBORNE |
Contact Information
| Contractor | L A Construction Group Inc; Lic. No.: 873259-B | 18607 VENTURA BLVD #205 TARZANA, CA 91356 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 6250 CANOGA AVE #525 WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Inspection | 9/28/2021 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 10/14/2021 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 10/14/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 10/20/2021 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/26/2021 | Approved | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 10/27/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 10/27/2021 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 11/3/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 11/5/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/18/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/19/2021 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 11/19/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 11/19/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 12/1/2021 | Partial Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 12/10/2021 | Partial Approval | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 12/10/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 12/10/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/14/2022 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | MATT KELLERMAN |
| Green Building Rough | 1/18/2022 | Approved | MATT KELLERMAN |
| Insulation | 1/21/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 1/25/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/25/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 3/18/2022 | Conditional Approval | THOMAS FINNILA |
| HVAC-Final | 3/18/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 3/18/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Final | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| Verify Rec and Parks Fee Memo | 3/23/2022 | No Access for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 3/25/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 3/25/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 3/25/2022 | Approved | THOMAS FINNILA |
| Final | 5/13/2022 | No Access for Inspection | THOMAS FINNILA |
| Green Building Final | 5/13/2022 | No Access for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 5/13/2022 | No Access for Inspection | THOMAS FINNILA |
| Final | 7/25/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 7/25/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 7/25/2022 | Approved | THOMAS FINNILA |
| Final | 8/4/2022 | OK to Issue CofO | THOMAS FINNILA |