4623 N BURNET AVE 91403

Certificate Information: 4623 N BURNET AVE 91403

Application / Permit
21016-20000-07972
Plan Check / Job No.
B21VN03746
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel kitchen and dining room. Relocate laundry. Remove portion of bearing walls per design.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
Permit Finaled on 9/3/2021

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 ANGELICA DAVE
Corrections Issued 4/7/2021 ANGELICA DAVE
Plan Check Approved 5/7/2021 ANGELICA MARTINEZ
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 5/12/2021 APPLICANT
Permit Finaled 9/3/2021 ADAM ESCOTO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Alin Design Inc; Lic. No.: 878427-B 16035 BLACKHAWK STREET      GRANADA HILLS, CA 91344
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/4/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/21/2021 Approved CHARLES POWELL
PLUMBING-Rough 6/21/2021 Partial Approval CHARLES POWELL
Underground Mechanical 6/21/2021 Not Ready for Inspection CHARLES POWELL
Wood Frame 6/21/2021 Partial Approval CHARLES POWELL
Insulation 7/8/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 7/15/2021 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 7/15/2021 Corrections Issued CALEB MEISTER
Pre-Inspection 7/15/2021 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 7/20/2021 Approved JAVIER RAMOS JR
Drywall Nailing 7/20/2021 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/20/2021 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Not Ready CHARLES POWELL
ELECTRICAL-Final 8/31/2021 Corrections Issued ALIZAH MAYAGOITIA
Final 8/31/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 8/31/2021 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 8/31/2021 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 8/31/2021 Partial Inspection JUSTIN HAWLEY
Final 9/3/2021 Permit Finaled ADAM ESCOTO
Smoke Detectors 9/3/2021 Approved ADAM ESCOTO