7320-7322 N LINDLEY AVE 91335
Certificate Information: 7320-7322 N LINDLEY AVE 91335
- Application / Permit
- 21016-20000-07783
- Plan Check / Job No.
- B21VN03675
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE AND ADD IT TO THE (E) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ARCHITECT DESIGN
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Corrected on 10/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | ALFREDO JARA |
| Corrections Issued | 4/6/2021 | ALFREDO JARA |
| Issued | 4/19/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 8/11/2021 | VINCENT HANLEY |
| Re-Activate Permit | 8/13/2021 | JOHN JANSON |
| CofO Issued-Status Void | 8/13/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 8/13/2021 | JOHN JANSON |
| Permit Finaled | 10/5/2021 | JOHN JANSON |
| CofO Corrected | 10/5/2021 | JOHN JANSON |
| Permit Finaled | 10/5/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/7/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/20/2021 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/20/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/4/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 6/4/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 6/4/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/11/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/11/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/11/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/11/2021 | Approved | VINCENT HANLEY |
| Insulation | 6/16/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/22/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 6/22/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/11/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/11/2021 | Approved | VINCENT HANLEY |
| Final | 8/11/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 8/11/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/11/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/11/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/11/2021 | SGSOV Approved | VINCENT HANLEY |