9109 W OLIN ST 90034
Certificate Information: 9109 W OLIN ST 90034
- Application / Permit
- 21016-20000-07773
- Plan Check / Job No.
- B21VN03667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 18'-3"x 18'-2" TWO CAR DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS65852.2 (e) (1) (A). WORK PER ENGINEER.
- Permit Issued
- Issued on 8/16/2021
- Issuing Office
- Current Status
- CofO Issued on 11/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/4/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/4/2021 | TROY DEGUZMAN |
| Plan Check Approved | 8/9/2021 | TROY DEGUZMAN |
| Issued | 8/16/2021 | APPLICANT |
| CofO in Progress | 11/18/2022 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2022 | DANIEL ORRANTE |
| CofO Issued | 11/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2021 | ROSA SILVA |
| Sewer availability | Cleared | 4/16/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | ROSA SILVA |
| Grading Pre-Inspection | Cleared | 7/22/2021 | KIRK LINKLATER |
| Construction within easement | Cleared | 7/24/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 6250 CANOGA AVE #525 WOODLAND HILLS, CA 91367 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 8/23/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Partial Approval | EVAN COOPER |
| Sewer | 4/26/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/26/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| METHANE-Final | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| METHANE-Rough | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 10/26/2022 | Approved | JESUS RODRIGUEZ |
| Final | 11/17/2022 | Partial Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Required | JESUS RODRIGUEZ |