1231 S ORANGE DR 90019

Certificate Information: 1231 S ORANGE DR 90019

Application / Permit
21016-20000-07666
Plan Check / Job No.
B21VN03613
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 365 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 COLIN LOREDO
Corrections Issued 3/30/2021 COLIN LOREDO
Building Plans Picked Up 4/1/2021 APPLICANT
Plan Check Approved 5/4/2021 COLIN LOREDO
Issued 5/5/2021 APPLICANT
CofO in Progress 3/2/2022 STUART CHAPMAN
No Progress 3/9/2022 STUART CHAPMAN
CofO in Progress 4/18/2022 STUART CHAPMAN
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/6/2021 ROSA SILVA
Sewer availability Cleared 4/6/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 4/7/2021 ROSA SILVA

Contact Information

Contractor Done Right Home Remodeling Inc; Lic. No.: 1002689-B 1825 DE LA CRUZ BLVD #203      SANTA CLARA, CA 95050
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/13/2021 Not Ready for Inspection STUART CHAPMAN
Pre-Inspection 7/13/2021 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 7/30/2021 Corrections Issued RUBEN SALAS
Special/Order Compliance 7/30/2021 Partial Inspection SHAVONNE ESPINOZA
Underground Mechanical 8/5/2021 Partial Approval THOMAS LOGRASSO
Sewer 8/9/2021 Approved STUART CHAPMAN
Underground Mechanical 8/9/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/24/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 11/15/2021 No Access for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 2/2/2022 Not Ready for Inspection STUART CHAPMAN
Drywall Nailing 2/2/2022 Not Ready for Inspection STUART CHAPMAN
Final 2/2/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Final 2/2/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 2/2/2022 Not Ready for Inspection STUART CHAPMAN
METHANE-Final 2/2/2022 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 2/2/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 2/2/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 2/11/2022 Not Ready for Inspection AMY COLIN
Drywall Nailing 2/11/2022 Not Ready for Inspection AMY COLIN
Final 2/11/2022 Not Ready for Inspection AMY COLIN
Green Building Final 2/11/2022 Not Ready for Inspection AMY COLIN
Green Building Rough 2/11/2022 Not Ready for Inspection AMY COLIN
METHANE-Final 2/11/2022 Not Ready for Inspection AMY COLIN
METHANE-Rough 2/11/2022 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready AMY COLIN
Smoke Detectors 2/11/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 3/2/2022 Approved STUART CHAPMAN
Drywall Nailing 3/2/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 3/2/2022 Approved STUART CHAPMAN
Final 3/2/2022 OK to Issue CofO STUART CHAPMAN
Green Building Final 3/2/2022 Approved STUART CHAPMAN
Green Building Rough 3/2/2022 Approved STUART CHAPMAN
HVAC-Final 3/2/2022 Approved STUART CHAPMAN
METHANE-Final 3/2/2022 Approved STUART CHAPMAN
METHANE-Rough 3/2/2022 Approved STUART CHAPMAN
PLUMBING-Final 3/2/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 3/2/2022 Approved STUART CHAPMAN
Service/Power Release 4/18/2022 Approved STUART CHAPMAN