2473 S COLBY AVE 90064
Certificate Information: 2473 S COLBY AVE 90064
- Application / Permit
- 21016-20000-07580
- Plan Check / Job No.
- B21VN03576
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT (517 SQ FT) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 4/27/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/7/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/16/2022 | APPLICANT |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 5/14/2025 | KIRK SANDERS |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
| CofO Issued | 5/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/23/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 9/29/2021 | DYLAN SITTIG |
| Specific Plan | Cleared | 11/8/2021 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Vahram; Lic. No.: S6482 | 1102 SAN RAFAEL AVE GLENDALE, CA 91202 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/22/2022 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/11/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/16/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/8/2022 | Partial Approval | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/8/2022 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Approved | KENNETH NAGLE |
| HVAC-Rough | 6/8/2022 | Approved | KENNETH NAGLE |
| Shower Pan | 6/8/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 6/13/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | KENNETH NAGLE |
| MERV13>=Rough | 6/13/2022 | Approved | KENNETH NAGLE |
| Insulation | 6/17/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/28/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/6/2022 | Approved | KENNETH NAGLE |
| Sewer | 7/6/2022 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 11/7/2022 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 11/7/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/8/2022 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 11/8/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 11/9/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 11/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 11/14/2022 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 11/16/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 11/16/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 11/16/2022 | Approved | ASHLEY THOMPSON |
| Final | 12/19/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 12/19/2022 | Off-Hour Fees Due | |
| Green Building Final | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 12/19/2022 | Off-Hour Fees Due | |
| MERV13>=Final | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 12/19/2022 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/19/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/19/2022 | Off-Hour Fees Due | |
| Final | 5/13/2025 | OK to Issue CofO | KIRK SANDERS |