7915 N OSTROM AVE 91406

Certificate Information: 7915 N OSTROM AVE 91406

Application / Permit
21016-20000-07362
Plan Check / Job No.
B21VN03483
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(A), ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 7/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/26/2021 RARES BODEA
Corrections Issued 3/29/2021 RARES BODEA
Plan Check Approved 7/15/2021 RARES BODEA
Issued 10/8/2021 APPLICANT
CofO in Progress 7/12/2022 ALAN MORELOS
CofO Issued 7/16/2022 MICHAEL SMITH
Permit Finaled 7/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/5/2021 ADRIAN CASTRO
Sewer availability Cleared 4/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 ADRIAN CASTRO
Construction near power lines Cleared 6/9/2021 RIDWAN HARDY
Construction within easement Cleared 6/9/2021 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/3/2022 Approved RAUL OLAGI
PLUMBING-Rough 1/3/2022 Partial Approval RAUL OLAGI
Sewer 1/3/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/17/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/17/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 2/17/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/17/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 3/1/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 3/1/2022 Approved RAUL OLAGI
HVAC-Rough 3/1/2022 Approved RAUL OLAGI
PLUMBING-Rough 3/1/2022 Approved RAUL OLAGI
Underground Mechanical 3/1/2022 Approved RAUL OLAGI
Insulation 3/4/2022 Corrections Issued ALAN MORELOS
Interior/Exterior Lathing 3/4/2022 Partial Approval ALAN MORELOS
Special/Order Compliance 3/4/2022 Corrections Issued ALAN MORELOS
Shower Pan 3/8/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 3/23/2022 Approved RAUL OLAGI
Green Building Rough 3/23/2022 Approved RAUL OLAGI
Insulation 3/23/2022 Approved RAUL OLAGI
Drywall Nailing 3/29/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 5/12/2022 Corrections Issued RAUL OLAGI
Final 5/12/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/12/2022 Approved RAUL OLAGI
HVAC-Final 5/12/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 5/12/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 5/12/2022 Approved RAUL OLAGI
Final 6/14/2022 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved ALAN MORELOS
Final 6/27/2022 Not Ready for Inspection ALAN MORELOS
ELECTRICAL-Final 7/12/2022 Approved ALAN MORELOS
Final 7/12/2022 OK to Issue CofO ALAN MORELOS
HVAC-Final 7/12/2022 Approved ALAN MORELOS
PLUMBING-Final 7/12/2022 Approved ALAN MORELOS