11821 N BABBITT AVE 91344
Certificate Information: 11821 N BABBITT AVE 91344
- Application / Permit
- 21016-20000-07361
- Plan Check / Job No.
- B21VN03482
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE PORTION OF (E) COVERED PORCH AND ENCLOSE REMAINING 6'-2" X 6'-10" (E) COVERED PORCH TO RELOCATEE ENTRY AND REMODEL AT LIVING ROOM & REFRAME ROOF TO FLAT ROOF. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 3/25/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 4/14/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/15/2021 | APPLICANT |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 9/23/2021 | DAVID SCANTLIN |
| Permit Finaled | 4/14/2022 | MICHAEL SMITH |
| CofO Issued | 4/14/2022 | MICHAEL SMITH |
| Permit Finaled | 4/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/1/2021 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 4/5/2021 | BRIAN MILLER |
Contact Information
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19558 GAULT ST RESEDA, CA 91335 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/27/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/14/2021 | Corrections Issued | JEFFREY PARD |
| Interior/Exterior Lathing | 5/14/2021 | Approved | JEFFREY PARD |
| Wood Frame | 5/18/2021 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| METHANE-Rough | 5/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Drywall Nailing | 5/25/2021 | Partial Approval | CHARLES POWELL |
| Wood Frame | 5/25/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 6/15/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 6/15/2021 | Approved | DAVID SCANTLIN |
| METHANE-Final | 6/15/2021 | Approved | DAVID SCANTLIN |
| METHANE-Rough | 6/15/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 6/21/2021 | Approved | JUSTIN HAWLEY |
| Final | 6/25/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 6/25/2021 | Approved | DAVID SCANTLIN |
| Final | 9/7/2021 | No Access for Inspection | VINCENT HANLEY |
| Final | 9/23/2021 | OK to Issue CofO | DAVID SCANTLIN |