3445 S 5TH AVE 90018

Certificate Information: 3445 S 5TH AVE 90018

Application / Permit
21016-20000-07247
Plan Check / Job No.
B21VN03422
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 LUISANGEL VALENZUELA
Corrections Issued 4/5/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/18/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/23/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/12/2021 LUISANGEL VALENZUELA
Issued 1/27/2022 APPLICANT
Building Plans Picked Up 1/27/2022 APPLICANT
CofO in Progress 8/8/2023 STUART CHAPMAN
Permit Finaled 8/8/2023 DEROLD HAUFF
CofO Issued 8/8/2023 DEROLD HAUFF
Permit Finaled 8/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/27/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 7/27/2021 JEANIE LAM
Sewer availability Cleared 7/27/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/2/2021 JEANIE LAM
HPOZ Cleared 1/18/2022 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/9/2022 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/9/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/9/2022 Approved STUART CHAPMAN
Insulation 5/9/2022 Corrections Issued STUART CHAPMAN
Sewer 5/9/2022 Approved STUART CHAPMAN
Underground Mechanical 5/9/2022 Corrections Issued STUART CHAPMAN
Insulation 5/19/2022 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/20/2022 Partial Approval SCOTT FINNILA
Green Building Rough 5/20/2022 Partial Approval SCOTT FINNILA
Deputy Drilled-In Anchors 6/1/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 6/6/2022 Approved STUART CHAPMAN
HVAC-Rough 6/6/2022 Approved STUART CHAPMAN
Insulation 6/6/2022 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 6/6/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 6/20/2022 Partial Approval STUART CHAPMAN
Insulation 6/20/2022 Approved STUART CHAPMAN
PLUMBING-Rough 6/20/2022 Approved STUART CHAPMAN
Drywall Nailing 7/6/2022 Approved STUART CHAPMAN
Green Building Rough 7/6/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/6/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 11/21/2022 Approved STUART CHAPMAN
Final 11/21/2022 Corrections Issued STUART CHAPMAN
Green Building Final 11/21/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/21/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 8/1/2023 Approved STUART CHAPMAN
Final 8/1/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/1/2023 Approved STUART CHAPMAN
PLUMBING-Final 8/1/2023 Approved STUART CHAPMAN
Service/Power Release 8/1/2023 Approved STUART CHAPMAN