3445 S 5TH AVE 90018
Certificate Information: 3445 S 5TH AVE 90018
- Application / Permit
- 21016-20000-07247
- Plan Check / Job No.
- B21VN03422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/5/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/18/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/23/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/12/2021 | LUISANGEL VALENZUELA |
| Issued | 1/27/2022 | APPLICANT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| CofO in Progress | 8/8/2023 | STUART CHAPMAN |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| CofO Issued | 8/8/2023 | DEROLD HAUFF |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/27/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/27/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | JEANIE LAM |
| HPOZ | Cleared | 1/18/2022 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/9/2022 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/9/2022 | Approved | STUART CHAPMAN |
| Insulation | 5/9/2022 | Corrections Issued | STUART CHAPMAN |
| Sewer | 5/9/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/9/2022 | Corrections Issued | STUART CHAPMAN |
| Insulation | 5/19/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/20/2022 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/20/2022 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 6/1/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/6/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 6/6/2022 | Approved | STUART CHAPMAN |
| Insulation | 6/6/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/6/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/20/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/20/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/20/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/6/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/6/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/6/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | STUART CHAPMAN |
| Final | 11/21/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 11/21/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 11/21/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/1/2023 | Approved | STUART CHAPMAN |
| Final | 8/1/2023 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 8/1/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/1/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 8/1/2023 | Approved | STUART CHAPMAN |