11467 W THURSTON CIR 90049

Certificate Information: 11467 W THURSTON CIR 90049

Application / Permit
21016-20000-07212
Plan Check / Job No.
B21VN03395
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Non-structural remodel; convert 2nd flr study to new bedroom, convert laundry room to new bedroom, remodel bathrooms and kitchen. New windows and doors per plan.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
Permit Finaled on 5/19/2022

Permit Application Status History

Submitted 3/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/24/2021 ANGELICA DAVE
Corrections Issued 3/24/2021 ANGELICA DAVE
Plan Check Approved 5/12/2021 ANGELICA MARTINEZ
Issued 5/12/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
Permit Finaled 5/19/2022 CARLOS MATAMOROS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/3/2021 ANTHONY MAINEZ
Sewer availability Cleared 5/3/2021 ANTHONY MAINEZ

Contact Information

Contractor Imbuia Construction Inc; Lic. No.: 796602-B 4751 DEL MORENO DR      WOODLAND HILLS, CA 91364

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/19/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 5/26/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 6/2/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 6/29/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 6/29/2021 Partial Approval CARLOS MATAMOROS
MERV13>=Rough 6/29/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/2/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 7/7/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/16/2021 Partial Approval ADAM ESCOTO
HVAC-Rough 7/23/2021 Conditional Approval CARLOS MATAMOROS
Wood Frame 7/23/2021 Approved CARLOS MATAMOROS
Green Building Rough 7/27/2021 Approved CARLOS MATAMOROS
Insulation 7/27/2021 Approved CARLOS MATAMOROS
Shower Pan 7/27/2021 Approved CARLOS MATAMOROS
Drywall Nailing 8/3/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/2/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/25/2022 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 3/25/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 5/19/2022 Approved CARLOS MATAMOROS
Final 5/19/2022 Permit Finaled CARLOS MATAMOROS
MERV13>=Final 5/19/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 5/19/2022 Approved CARLOS MATAMOROS