5906 S SAN PEDRO ST 90003

Certificate Information: 5906 S SAN PEDRO ST 90003

Application / Permit
21016-20000-07175
Plan Check / Job No.
B21VN03362
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ALQ, (E) PATIO, (E)STAIRS AND (E)GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEERING.
Permit Issued
Issued on 8/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/26/2021 RAPHAEL ROSAS
Corrections Issued 3/28/2021 RAPHAEL ROSAS
Applicant returned to address corrections 8/23/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/9/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/11/2022 APPLICANT
Applicant returned to address corrections 5/2/2023 JESSE ARELLANO
Applicant returned to address corrections 8/1/2023 PINANK PATEL
Plan Check Approved 8/7/2023 GIOVANNY CHAVEZ
Issued 8/8/2023 APPLICANT
CofO in Progress 11/26/2024 ALEJANDRO DE ARTOLA
Permit Finaled 12/7/2024 DEROLD HAUFF
CofO Issued 12/7/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2021 STEVE MELGAR
Sewer availability Cleared 8/18/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/24/2021 STEVE MELGAR
Community Plan Implem. Overlay Cleared 8/2/2023 HELEN JADALI
ZI Cleared 8/2/2023 HELEN JADALI
Redevelopment Project Area Cleared 8/4/2023 YASMINE BASHIRI
ZI Cleared 8/4/2023 YASMINE BASHIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2024 Corrections Issued SABAS ALONSO
Pre-Inspection 4/25/2024 Partial Inspection SABAS ALONSO
Footing/Foundation/Slab 5/14/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 5/14/2024 Partial Approval MICHAEL LEWIS
Sewer 5/14/2024 Approved MICHAEL LEWIS
Underground Mechanical 5/14/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/23/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 5/29/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/3/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/3/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/23/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/23/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/30/2024 Corrections Issued ALEX COLIN
BUILDING-Rough-Frame 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 8/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/1/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/20/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 8/20/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/27/2024 Approved ALEJANDRO DE ARTOLA
Insulation 9/10/2024 Conditional Approval ALEJANDRO DE ARTOLA
Underground Mechanical 9/10/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/26/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 11/8/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/14/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/14/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/14/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/25/2024 Approved ALEJANDRO DE ARTOLA
Final 11/25/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 11/25/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/25/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/25/2024 Approved ALEJANDRO DE ARTOLA