20741 1/2 W LEMAY ST 91306
Certificate Information: 20741 1/2 W LEMAY ST 91306
- Application / Permit
- 21016-20000-07117
- Plan Check / Job No.
- B21VN03347
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). FIRE SPRNKLER REQUIRED NFPA-13D.
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 5/1/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/18/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/27/2021 | SERGIO MUNIZ |
| Issued | 7/28/2021 | APPLICANT |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| CofO in Progress | 5/11/2022 | SEAN WIRCH |
| CofO Issued | 5/11/2022 | MICHAEL SMITH |
| Permit Finaled | 5/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/7/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2021 | ADRIAN CASTRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2022 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/20/2022 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/20/2022 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 1/21/2022 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 2/1/2022 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 2/1/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 2/1/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | SEAN WIRCH |
| Insulation | 2/10/2022 | Partial Approval | SEAN WIRCH |
| Wood Frame | 2/10/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 2/18/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/22/2022 | Corrections Issued | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 3/17/2022 | Not Ready for Inspection | SEAN WIRCH |
| Gas Test | 3/22/2022 | Approved | SEAN WIRCH |
| PLUMBING-Final | 3/25/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 4/4/2022 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | SEAN WIRCH |
| Final | 5/10/2022 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 5/10/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 5/10/2022 | Approved | SEAN WIRCH |
| HVAC-Final | 5/10/2022 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 5/10/2022 | Approved | SEAN WIRCH |
| Service/Power Release | 5/12/2022 | Approved | SEAN WIRCH |