3836 S LYCEUM AVE 90066
Certificate Information: 3836 S LYCEUM AVE 90066
- Application / Permit
- 21016-20000-07093
- Plan Check / Job No.
- B21VN03334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) 1-STORY SFD W/ ATTACHED GARAGE: CONVERT PORTION OF (E) GARAGE INTO LAUNDRY ROOM (4'-0" X 6'-1"), ADD & REMOVE NON-BEARING WALLS
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/28/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/12/2021 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| Issued | 5/26/2021 | APPLICANT |
| CofO in Progress | 6/14/2025 | DAVID FEILER |
| Permit Finaled | 6/17/2025 | RICHARD STEINBACH |
| CofO Issued | 6/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hildebrandt Contracting And Development; Lic. No.: 865585-B | 4157 NEOSHO AVE LOS ANGELES, CA 90066 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/3/2021 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/3/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/3/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/3/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 6/3/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/8/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/8/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/8/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 6/23/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/25/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/3/2021 | Approved | ANDREW NAVE |
| Final | 8/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/27/2021 | Approved | ENRIQUE MIRELES |
| Final | 6/14/2025 | OK to Issue CofO | DAVID FEILER |